There are a variety of concrete mixes shown in the Detailed Construction Guide that comes with the machines which may be used for different applications and depending on the materials available in your immediate area.
The most common used 15 to 20 MPa mix is:
2 x |
Building sand |
(2 wheelbarrows) |
1 x |
Cement (2 pockets of 32.5) |
(2 pockets of cement) |
30ltr x |
Water |
(30 liters of water) |
CONCRETE STRENGTHS
Recommended mixes detailed in the Construction Guide are:
Perimeter wall under 1.8m high, shed, bird or small animal enclosure |
5 – 10 MPa |
Perimeter wall over 1.8m high |
0 – 15 MPa |
Single and double storey houses (depending on the wind loading) |
15 – 20 MPa |
Reservoirs and large animal enclosures |
20 – 25 MPa |
Retaining walls |
25 – 30 MPa |
MATERIAL USAGE
One of the biggest attractions of using FinnBUILDER™ is that it is a lot less expensive than building with brick or blocks. See Cost Comparisons for further detail on this. You can calculate the amount of material that you need to use following this simple guide:
1. |
Decide whether your walls will be 220 mm thick, 150 mm thick or 110 mm thick. |
2. |
From your plans, measure the length of you walls and the height. |
|
Calculate the area of your walls by multiplying the length by the height. e.g. if the wall is 50 meters long and 2 meters high, the area of the wall is 100 m2. A cement pocket weights 50kgs and costs about R 70.00 each |
Calculate quantities required and cost based on wall of 100m2
Tickness of wall
|
Aggregate needed / m2
|
Cement needed / m2
|
Total aggregate needed
|
Total cement needed
|
Cost of aggregate @ R150 / m3
|
Cost of cement @ R70 / pkt.
|
220mm
|
0.253m3
|
43kg
|
= 25.3m3
|
= 86 pkts
|
= R 3 795
|
= R 6 020
|
150mm
|
0.13m3
|
29kg
|
= 17.3m3
|
= 58 pkts
|
= R 2 595
|
= R 4 060
|
110mm
|
0.127m3
|
21kg
|
= 12.7m3
|
= 42 pkts
|
= R 1 905
|
= R 2 940
|
Total aggregate needed will be divided up on the ratio of the mix that you have elected to use as per the Detailed Construction Guide.
DOUBLE STOREY HOMES
Since 1946 double storey homes have been built using FinnBUILDER. Examples are shown in the Gallery.
FOUNDATIONS
The plans for your house or structure must be drawn by a qualified architect or architectural designer, who will need a Civil Engineer to specify the type and thickness of the foundations that you need to pour, given your soil conditions and the loadings that your structure will carry. Generally foundation trenches will be a minimum of 600mm deep below natural ground level (NGL), and 650mm wide for external walls and 450mm wide for internal walls.
Foundations are a critical part of any building. If you are not a civil engineer, make sure that you have dug your foundation trenches down to firm footing throughout the trenches, and then call in the Municipal Inspector and the professional engineer to inspect your foundation trenches and approve them before you throw your concrete.
Once your foundation trenches have been approved, use a foundation concrete mix of 3 wheelbarrows 19mm concrete stone, 3 wheelbarrows of river sand and 2 pockets of cement plus 80 liters of water to throw your foundations 200mm thick. Double storey foundations will vary in depth.
Retaining walls can be inexpensively built using the system. Once again the design of the wall is a technical issue which must be properly addressed by a professional engineer. Vertical steel running out of the foundations and into the wall, structural piers and adequate drainage ports are some of the design elements which needs to be considered.
SABS TESTING
SABS testing has taken place on our concrete mixes to confirm that they achieve the required strength.
NHBRC
The NHBRC is now the watchdog of the building industry and under new legislation during the last fifteen years, new building projects have to be approved and enrolled with the council before bank financing can be granted.
The NHBRC has approved our FinnBUILDER RATIONAL DESIGN and will enroll sites that will be building using the system. The requirements of the NHBRC include the appointment of a Competent Person to monitor construction with the QUALITY MANAGEMENT SYSTEM and who will be responsible for signing off that the building has been built in accordance with the RATIONAL DESIGN.
MUNICIPAL REQUIREMENTS
Once the requirements of the NHBRC have been met, Municipalities in South Africa will accept your plans. If they have further questions, you are welcome to refer them to ourselves so that we can answer any further technical questions that they may have.
The plans that you submit to the Municipality to specify that you will be building with “slip form concrete shuttering, using 15MPa no-slump concrete”.
AGREMENT CERTIFICATION
Now that we have full NHBRC Accreditation, it is no longer necessary for us to persue Agrement Certification. The system already enjoys acceptance throughout Africa and many other countries in the world. For this reason we are no longer persuing Agrement Certification. |