Require 40 kgs of cement per m2 |
|
|
|
200 m2 = 160 bags @ R 66.00 / bag excl. |
R 10 560.00 |
|
|
Allowance for Y 10 reinforcing steel |
R 200.00 |
|
|
Total Materials for walling using FinnBUILDER |
R 18 166.00 |
|
|
|
|
|
|
Blocks 3,5 Mpa |
|
|
|
200 m2 x 13,5 blocks / m2 = |
|
|
|
equals 2 700 blocks @ R 6.70 e.a. excl. |
|
R 18 090.00 |
|
Building sand 1m3 / 70 blocks = 39 m3 |
|
|
|
39 m3 @ R 120.00 m3 |
|
R 4 680.00 |
|
Cement – require 5.5 bags cement per m3 of building sand |
|
|
|
= 39 m3 x 5.5 bags @ R 66.00
|
|
R 14 157.00 |
|
Total Materials for walling using bricks |
|
R 36 927.00 |
|
|
|
|
|
Cost per Square Meter of vertical wall |
R 90.83 |
R 184.64 |
R 93.81 |
|
R 18 166.00 |
R 36 927.00 |
R 18 761.00 |
|
|
|
|
Labour |
|
|
|
FinnBUILDER |
|
|
|
The industry norm for a FinnBUILDER team provided |
|
|
|
with 4 FinnBUILDER machines to build with |
|
|
|
is R 28.50 / m2 of vertical walling |
R 28.50 |
|
|
|
|
|
|
Blocks (13,5 blocks needed per m2 of walling) |
|
|
|
The industry norm for Blocklayers is |
|
|
|
R 2.50 per block laid. |
|
|
|
Therefore cost per m2 is R 2.50 per block x 13.5 blocks / m2 |
|
R 33.75 |
|
|
|
|
|
Cost per Square Meter of vertical wall |
R 28.50 |
R 33.75 |
R 5.25 |
|
R 5 700.00 |
R 6 750.00 |
R 1 050.00 |
|
|
|
|
Plastering |
|
|
|
FinnBUILDER |
|
|
|
Nil |
|
|
|
|
|
|
|
Bricks |
|
|
|
Plaster sand: Plaster 15 mm thick both sides. |
|
Asume no plaster but a cementious painted used to finish walls
|
|
Need 0.021 m3 of plaster sand per 1 m2 of wall |
|
|
‘@ R 265.00 /m3 = R 5,57 one side of the wall |
|
|
Cement: Need 1 pocket of cement to plaster 3 m2 of wall |
|
|
@ R 66.00 per pocket / 3 m2 one side of the wall |
|
|
Labour: R 18/ m2 one side of the wall. |
|
|
|
|
|
|
Cost per Square Meter of vertical wall |
|
|
|
|
|
|
|
Floating |
|
|
|
Finish the walls with a float mix 3 mm thick on both sides. |
Assume no floating of walls but a cementious painted used to finish walls
|
|
|
Plaster sand: Need 0.005m3 of plaster sand per 1 m2 of wall. |
|
|
‘@ R 265.00 / m3 = R 1.33 / m2 one side of the wall |
|
|
Cement: Need 1 pocket of cement to float 14 m2 of wall |
|
|
‘@ R 66.00 per pocket = R 66.00 / 14 m2 one side of the wall |
|
|
Labour: R 8 / m2 one side of the wall |
|
|
|
|
|
|
Cost per Square Meter of vertical wall |
|
|
R 0.00 |
|
|
|
R 0.00 |
|
|
|
|
Total Cost Comparison |
R 119.33 |
R 218.39 |
R 99.06 |
|
R 23 866.00 |
R 43 677.00 |
R 19 811.00 |
|
|
|
|
Note: The cost of DPC, brickforce, windows, door frames, lintels and roof tie in wire have been ignored because costs are the same for both FinnBUILDER and Brick. |
|
|
|